Roads24CC0251

NETWORK DEV. PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PULILAN-CALUMPIT RD - K0043+(-142) - K0043+140, K0043+690 - K0044+419, K0046+463 - K0046+513, K0046+614 - K0046+814, K0047+013 - K0047+104, K0047+120 - K0047+127, K0047+228 - K0047+943

NETWORK DEV. PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PULILAN-CALUMPIT RD - K0043+(-142) - K0043+140, K0043+690 - K0044+419, K0046+463 - K0046+513, K0046+614 - K0046+814, K0047+013 - K0047+104, K0047+120 - K0047+127, K0047+228 - K0047+943 is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱19,890,667.98. Status: Reported complete (DPWH). Contractor on record: PRIME PAVE CONST AND ASPHALT CORP. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

103 projects · ₱3.6B total · 0 flags

4. Implementation

Contract Amount

₱19,890,667.98

Progress

Reported complete (DPWH)

Start Date

April 2, 2024

Target End

October 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.