CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TALOMO RIVER, NHA BANGKAL SECTION, LEFT BANK, DAVAO CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TALOMO RIVER, NHA BANGKAL SECTION, LEFT BANK, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: AGONG BUILDERS AND CONST SUPPLY INC. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-20-0014285

₱668,342.00 · FY2020

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

December 17, 2020

Target End

December 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.