Buildings and Facilities16DP0033

CONSTRUCTION OF CRISTOBAL S. CONDUCTO MNHS, RIZAL, LAGUNA, THREE (3) STOREY SIX (6) CLASSROOMS

CONSTRUCTION OF CRISTOBAL S. CONDUCTO MNHS, RIZAL, LAGUNA, THREE (3) STOREY SIX (6) CLASSROOMS is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱11,087,193.30. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱11,087,193.30

Progress

Reported complete (DPWH)

Start Date

August 7, 2016

Target End

February 2, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.