Roads24II0018

ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0805+836-K0806+200, 2ND DISTRICT NORTHERN SAMAR

ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0805+836-K0806+200, 2ND DISTRICT NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱29,862,134.72. Status: Reported complete (DPWH). Contractor on record: KT CHAN CONST. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Catubig Flood Control Structure, Catubig, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0018688

₱738,259.00 · FY2024

Released to Sulu State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,862,134.72

Progress

Reported complete (DPWH)

Start Date

February 5, 2024

Target End

August 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.