Buildings and Facilities23GL0119

CONSTRUCTION OF MULTI-PURPOSE BUILDING, 2ND NEGROS OCCIDENTAL PROVINCIAL MOBILE FORCE COMPANY, HINIGARAN, NEGROS OCCIDENTAL REGION VI

CONSTRUCTION OF MULTI-PURPOSE BUILDING, 2ND NEGROS OCCIDENTAL PROVINCIAL MOBILE FORCE COMPANY, HINIGARAN, NEGROS OCCIDENTAL REGION VI is a DPWH-tracked public work in Negros Occidental 2nd DEO, Negros Island Region. Reported contract value: ₱4,825,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: J LEE CONST CORP FORMERLY: J LEE 09876. Figures trace to dpwh.

Negros Occidental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱26,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Matagoy Creek, Silay City, Negros Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Occidental 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,825,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

November 28, 2023

Target End

February 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.