Roads24K00363

PREVENTIVE MAINTENANCE-PRIMARY ROADS, SAYRE HIGHWAY-K1488+324-K1490+088,K1490+122-K1490+970,K1491+175,K1492+000,K1493+805-K1494+000

PREVENTIVE MAINTENANCE-PRIMARY ROADS, SAYRE HIGHWAY-K1488+324-K1490+088,K1490+122-K1490+970,K1491+175,K1492+000,K1493+805-K1494+000 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱136,882,423.04. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱136,882,423.04

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 10, 2024

Target End

January 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.