Flood Control and Drainage25NG0003

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SURIGAO RIVER, PHASE II, SITIO KABALAWAN/BARANGAY RIZAL, SURIGAO CITY, SURIGAO DEL NORTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SURIGAO RIVER, PHASE II, SITIO KABALAWAN/BARANGAY RIZAL, SURIGAO CITY, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 2nd DEO, Region XIII. Reported contract value: ₱72,375,000.00. Status: Past target date (DPWH On-Going). Contractor on record: A T DUMLAO CONST INC FORMERLYANDONI T D. Figures trace to dpwh.

Surigao del Norte 2nd DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Purok 2, Brgy. Urbiztondo, Claver, Surigao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-25-0016891

₱1,680,345.00 · FY2025

Released to Regional Office - VIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Past target date (DPWH On-Going)

Start Date

February 26, 2025

Target End

January 26, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.