Buildings and Facilities22EH0120

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PANIQUE, ODIONGAN, ROMBLON

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PANIQUE, ODIONGAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱1,940,000.00. Status: Reported complete (DPWH). Contractor on record: R N V CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Palo-o Flood Control Structure, Odiongan, Romblon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0009450

₱130,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱1,940,000.00

Progress

Reported complete (DPWH)

Start Date

June 29, 2022

Target End

August 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.