Water Provision and Storage20DD0323

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATER SYSTEM AT BRGY. DUHATAN, LIPA CITY, BATANGAS

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATER SYSTEM AT BRGY. DUHATAN, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱2,878,000.00. Status: Reported complete (DPWH). Contractor on record: OIC CONZTRUCT AND SUPPLY CORP FORMERLY:OIC CONST. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structure at Brgy. Tambo, Lipa City, Batangas
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-20-0008301

₱127,660,800.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

265 projects · ₱2.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, TAAL LAKE CIRCUMFERENTIAL ROAD (BALETE-MATAAS NA KAHOY SECTION), BALETE AND MATAAS NA KAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2020₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF MALVAR-BALETE DIVERSION RO

Batangas 3rd DEO, Region IV-A

2022₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, TINGLOY CIRCUMFERENTIAL ROAD, BATANGAS PACK

Batangas 2nd DEO, Region IV-A

2024₱94.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF TINGLOY CIRCUMFERENTIAL ROA

Batangas 2nd DEO, Region IV-A

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION, REHABIL

Batangas 3rd DEO, Region IV-A

2018₱77.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, BAUAN-MABINI RD -K0174+000 - K0174+945, K0175+100 - K0175+300, K0175+7

Batangas 2nd DEO, Region IV-A

2022₱67.5M
Reported complete (DPWH)
View all 265 projects →

4. Implementation

Contract Amount

₱2,878,000.00

Progress

Reported complete (DPWH)

Start Date

October 14, 2020

Target End

January 11, 2021