Roads16HK0104

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING T

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING T is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱18,633,259.40. Status: Reported complete (DPWH). Contractor on record: QM BUILDERS. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagtic Flood Control along Dumaguete North Road, Sitio Bagtic, Brgy. Lucay, Manjuyod, Negros Oriental
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-17-0012607

₱-4,999.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

769 projects · ₱47.1B total · 123 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO -BRGY. MANLAPAY, DUMANJUG, CEBU

Region VII, Region VII

2025₱359.4M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), POBLACION, DUMANJUG, CEBU

Region VII, Region VII

2024₱313.6M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONST.OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE, AND LANDSLIDE, SECONDARY ROADS,CEBU TOLEDO WHARF ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING

Region VII, Region VII

2016₱295.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, ROAD CONCRETING OF SRP BACK ROAD (PHASE III)

Region VII, Region VII

2023₱289.4M
Past target date (DPWH On-Going)
No sat.

MF0-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES , SECONDARY ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING,) K0011+237-K0013+245, K0016+50

Region VII, Region VII

2017₱289.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF ROAD, BARANGAY LIBO-BARANGAY GUIBANGCO-AN, SIBONGA, CEBU PHASE 2

Region VII, Region VII

2025₱283.7M
Past target date (DPWH On-Going)
View all 769 projects →

4. Implementation

Contract Amount

₱18,633,259.40

Progress

Reported complete (DPWH)

Start Date

May 10, 2017

Target End

September 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.