Flood Control and Drainage24OE0009

CONSTRUCTION OF PUMPING STATION ALONG ESTERO DE SAN MIGUEL (EARNSHAW DRAINAGE MAIN OUTFALL)

CONSTRUCTION OF PUMPING STATION ALONG ESTERO DE SAN MIGUEL (EARNSHAW DRAINAGE MAIN OUTFALL) is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱96,465,554.80. Status: Past target date (DPWH On-Going). Contractor on record: GOLDEN J'S CONST SERVICES 51135. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de San Miguel, Barangay 385, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

North Manila DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 51135

34 projects · ₱2.8B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE- SECONDARY ROADS- MOGPOG-BALANACAN PORT OAD- K0012+763=-K0013+500 (INTERMITTENT SECTIONS), MARINDUQUE

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG MINDORO WEST COASTAL ROAD, K0353+000-K0369+000 (INTERMITTENT SECTIONS), OCC. MINDORO

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. PROPER, STA. 000+000-STA. 000+368.64, BANSUD, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. TAMBONG, STA. 000=000-STA. 000+332.94, GLORIA, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.2M
Past target date (DPWH On-Going)
No sat.

CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.2M
Past target date (DPWH On-Going)
No sat.

CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.0M
Past target date (DPWH On-Going)
View all 34 projects →

4. Implementation

Contract Amount

₱96,465,554.80

Progress

Past target date (DPWH On-Going)

Start Date

February 8, 2024

Target End

March 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.