Roads19LB0051

CONSTRUCTION OF ROAD SLOPE STRUCTURE ALONG FATIMA-MALABOG ROAD (S00059MN), K1503+970-K1504+050 RS,K1506+150-K1506+230 BS,K1508+440-K1508+510 LS,K1509+515-K1509+550 LS,K1512+125-K1512+165 RS, K1512+319-K1512+369 RS

CONSTRUCTION OF ROAD SLOPE STRUCTURE ALONG FATIMA-MALABOG ROAD (S00059MN), K1503+970-K1504+050 RS,K1506+150-K1506+230 BS,K1508+440-K1508+510 LS,K1509+515-K1509+550 LS,K1512+125-K1512+165 RS, K1512+319-K1512+369 RS is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱95,783,970.00. Status: Reported complete (DPWH). Contractor on record: RELY CONST. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-19-0003090

₱180,662.00 · FY2019

Released to Regional Field Unit - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱95,783,970.00

Progress

Reported complete (DPWH)

Start Date

July 31, 2019

Target End

March 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.