Roads20CC0011

REHABILITATION OF BARANGAY ROAD AT STA. ANA, BULACAN, BULACAN

REHABILITATION OF BARANGAY ROAD AT STA. ANA, BULACAN, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱1,939,606.80. Status: Reported complete (DPWH). Contractor on record: JCL BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱48,594,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Angat River, Makinabang Section, Sta. 00+000 to Sta. 00+353.60, Baliuag, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-20-0007526

₱1,558,081.00 · FY2020

Released to Muntinlupa Business High School (Pedro E. Diaz High School-Buli Annex) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,939,606.80

Progress

Reported complete (DPWH)

Start Date

February 12, 2020

Target End

April 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.