Buildings and Facilities16DB0039

CONSTRUCTION OF DAY CARE CENTER, BRGY. BOLBOK, TUY, BATANGAS 1ST LD

CONSTRUCTION OF DAY CARE CENTER, BRGY. BOLBOK, TUY, BATANGAS 1ST LD is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱2,940,303.33. Status: Reported complete (DPWH). Contractor on record: RICH ADS CONST CORP FORMERLY RICH ADS CON. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,940,303.33

Progress

Reported complete (DPWH)

Start Date

March 18, 2016

Target End

June 30, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.