Buildings and Facilities17LA0321

CONSTRUCTION OF ONE (1) UNIT, TWO (2) STOREY, EIGHT (8) CLASSROOM BUILDING @ KATIPUNAN ES, NABUNTURAN (CAPITAL), COMPOSTELA VALLEY PROVINCE

CONSTRUCTION OF ONE (1) UNIT, TWO (2) STOREY, EIGHT (8) CLASSROOM BUILDING @ KATIPUNAN ES, NABUNTURAN (CAPITAL), COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱18,358,743.85. Status: Reported complete (DPWH). Contractor on record: R SEMILLA CONST. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱18,358,743.85

Progress

Reported complete (DPWH)

Start Date

December 28, 2017

Target End

August 24, 2018

5. Audit