Buildings and Facilities23GH0061

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BORONGON, SAN DIONISIO, ILOILO

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BORONGON, SAN DIONISIO, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱1,960,190.52. Status: Reported complete (DPWH). Contractor on record: CONTE BUILDERS. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Anono-o Flood Control Project, Barangay Anono-o, Guimbal, Iloilo
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-23-002520

₱388,924.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱1,960,190.52

Progress

Reported complete (DPWH)

Start Date

February 28, 2023

Target End

June 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.