Buildings and Facilities20EH0027

CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. AZAGRA, SAN FERNANDO, ROMBLON

CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. AZAGRA, SAN FERNANDO, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,865,310.86. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱29,740,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Olango Flood Control, San Fernando, Romblon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-20-0010705

₱724,722.00 · FY2020

Released to Pampanga 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,112 projects · ₱59.5B total · 113 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱297.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island Romblon

ALCANTARA (ROMBLON), ROMBLON, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
View all 1,112 projects →

4. Implementation

Contract Amount

₱4,865,310.86

Progress

Reported complete (DPWH)

Start Date

February 19, 2020

Target End

September 15, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.