Flood Control and Drainage16FC0052

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES ALONG PRINCIPAL RIVERS, LABO RIVER ,BRGY.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES ALONG PRINCIPAL RIVERS, LABO RIVER ,BRGY. is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱25,112,900.56. Status: Reported complete (DPWH). Contractor on record: VARIN CONST AND HARDWARE SUPPLY FORMERLY: VC VARIN CONST AND HARDWARE SUPPLY. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱25,112,900.56

Progress

Reported complete (DPWH)

Start Date

December 13, 2016

Target End

June 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.