Roads25L00148

CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DEL MONTE TO BARANGAY TAGBAY, SAMAL DISTRICT, ISLAND GARDEN CITY OF SAMAL, DAVAO DEL NORTE

CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DEL MONTE TO BARANGAY TAGBAY, SAMAL DISTRICT, ISLAND GARDEN CITY OF SAMAL, DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱47,506,240.36. Status: Past target date (DPWH On-Going). Contractor on record: COASTLAND CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱47,506,240.36

Progress

Past target date (DPWH On-Going)

Start Date

September 18, 2025

Target End

February 19, 2026

5. Audit