Flood Control and Drainage21FK0055

CLUSTER XVI- 1.) REPAIR/REHAB. OF SAN RAFAEL BRIDGE ABUTMENT PROTECTION AND CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG DANCALAN-STA. CRUZ-PIO DURAN ROAD SECTION & 2.) REPAIR/REHAB. OF DANCALAN BRIDGE ABUTMENT PROTECTION AND

CLUSTER XVI- 1.) REPAIR/REHAB. OF SAN RAFAEL BRIDGE ABUTMENT PROTECTION AND CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG DANCALAN-STA. CRUZ-PIO DURAN ROAD SECTION & 2.) REPAIR/REHAB. OF DANCALAN BRIDGE ABUTMENT PROTECTION AND is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱2,340,780.27. Status: Reported complete (DPWH). Contractor on record: RGE CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱8,800,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Salvador H. Escudero III Diversion Road, Sorsogon River, Downstream, Sorsogon City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Sorsogon DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,340,780.27

Progress

Reported complete (DPWH)

Start Date

July 15, 2021

Target End

October 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.