Buildings and Facilities17LE0186

CONSTRUCTION OF 2 STY. 4 CL WORKSHOP BUILDING (7 X 18), JOSE DE ARCE MHS ( SANGKOKDATAL), SARANGANI, DAVAO OCCIDENTAL

CONSTRUCTION OF 2 STY. 4 CL WORKSHOP BUILDING (7 X 18), JOSE DE ARCE MHS ( SANGKOKDATAL), SARANGANI, DAVAO OCCIDENTAL is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱8,704,125.84. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,704,125.84

Progress

Reported complete (DPWH)

Start Date

January 18, 2018

Target End

May 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.