Buildings and Facilities18MG0039

CONSTRUCTION (COMPLETION) OF BARANGAY GYM, BRGY. CONCEPCION, KORONADAL CITY, SOUTH COTABATO

CONSTRUCTION (COMPLETION) OF BARANGAY GYM, BRGY. CONCEPCION, KORONADAL CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱1,379,881.53. Status: Reported complete (DPWH). Contractor on record: ROCKSTONE CONST SERVICES. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,379,881.53

Progress

Reported complete (DPWH)

Start Date

March 7, 2018

Target End

July 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.