Flood Control and Drainage25JI0012

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG RD, PART OF SIBUGUEY RIVER, BARANGAY PILAR, DIPLAHAN, ZAMBOANGA SIBUGAY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG RD, PART OF SIBUGUEY RIVER, BARANGAY PILAR, DIPLAHAN, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱48,949,372.39. Status: Past target date (DPWH On-Going). Contractor on record: ESR CONST AND DEVELOPMENT CORP FORMERLY: ESR CONST. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Imelda-Bayog-Kumalarang-Lapuyan-Margosatubig Rd, part of Sibuguey River, Barangay Pilar, Diplahan, Zamboanga Sibugay
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zamboanga Sibugay 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

335 projects · ₱24.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF CONCRETE ROAD AND ROAD SLOPE PROTECTION STRUCTURE BALIGUIAN COASTAL ROAD, JUNCTION BALIGUIAN - KAUSWAGAN - MAMAD SECTION, ZAMBOANGA DEL NORTE, 2ND DEO, K2043+170.00 - K2044+410.00, K2044+810.00 - K2046+464.00, NET LENGTH: 5.79 LANE KM/2,8

Region IX, Region IX

2018₱280.6M
Reported complete (DPWH)
No sat.

CONCRETING OF ZAMBOANGA DEL SUR COASTAL ROAD, ZAMBOANGA DEL SUR (2ND DEO), CHAINAGE 0 - CHAINAGE 3008.75; CHAINAGE 6000 - CHAINAGE 7542.78; CHAINAGE 28510 - CHAINAGE 29558.80; CHAINAGE 97 - CHAINAGE 1097; CHAINAGE 940.00 - CHAINAGE 1979.62; CHAINAGE 21157

Region IX, Region IX

2016₱276.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS LABANGAN - PAGADIAN CITY - DUMALINAO ZDS BY-PASS ROAD, INCLUDING ROW, ZAMBOANGA DEL SUR

Region IX, Region IX

2018₱215.6M
Reported complete (DPWH)
No sat.

CONCRETING OF ROAD LUUK - PANAMAO - PATIKUL CIRCUMFERENTIAL ROAD, SULU 2ND LD, STA. 5+000.00 - STA. 10+280.00 (NET LENGTH: 5,280.00 LN.M.)

Region IX, Region IX

2016₱202.5M
Reported complete (DPWH)
No sat.

ROAD WIDENING DIPOLOG - SINDANGAN - LILOY ROAD, ZAMBOANGA DEL NORTE 1ST DEO, K1873+862.00 - K1875+233.00, K1875+377.00 - K1877+534.00, K1881+560.00 - K1884+449.95, K1884+449.95 - K1885+210.00, NET LENGTH: 14.36 LANE KM/7,178.00 LN.M./7.178 KM

Region IX, Region IX

2018₱187.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD ALONG NRJ BARANGAY CAMUL - NRJ BARANGAY LUMBAYAO PACKAGE 2, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱173.6M
Past target date (DPWH On-Going)
View all 335 projects →

4. Implementation

Contract Amount

₱48,949,372.39

Progress

Past target date (DPWH On-Going)

Start Date

February 26, 2025

Target End

October 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.