Buildings and Facilities24BE0142

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY PARAGU, TUMAUINI, ISABELA

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY PARAGU, TUMAUINI, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱2,964,621.26. Status: Reported complete (DPWH). Contractor on record: ARVEA'S CONST. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tunggui, Tumauini, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018087

₱-138,030,035.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

63 projects · ₱886.0M total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF COMPANIA FLOOD CONTROL,

Isabela 1st DEO, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

BIP - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION (COMPLETION) OF BRIDGE LINKING BRGY. CALIGAYAN - BRGY. ANTAGAN I TRAVERSING THE PINACANAUAN DE TUMAUINI RIVER (PHASE 2) TUMAUINI, ISABELA

Isabela 1st DEO, Region II

2023₱74.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING TUMAUINI, ISABELA

Isabela 1st DEO, Region II

2022₱49.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BARANGAY ANTAGAN 2ND FLOOD CONTROL SYSTEM, TUMAUINI, ISABELA

Isabela 1st DEO, Region II

2023₱49.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MUNICIPAL COMMUNITY HOSPITAL, BARANGAY LINGALING, TUMAUINI, ISABELA

Isabela 1st DEO, Region II

2025₱48.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP) - CONSTRUCTION OF ROADS LEADING TO TOURISM SITE PALLACOT WATERFALLS, CALIGAYAN, TUMAUINI

Isabela 1st DEO, Region II

2024₱29.4M
Reported complete (100% progress, DPWH status On-Going)
View all 63 projects →

4. Implementation

Contract Amount

₱2,964,621.26

Progress

Reported complete (DPWH)

Start Date

September 5, 2024

Target End

January 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.