Bridges18JD0043

REPLACEMENT OF PERMANENT WEAK BRIDGES-CONCRETE PAVING OF BRIDGE APPROACHES BAGO BRIDGE (BO1827MN) ALONG RIZAL-DAKAK-DAPITAN COASTAL LOOP ROAD, ZN

REPLACEMENT OF PERMANENT WEAK BRIDGES-CONCRETE PAVING OF BRIDGE APPROACHES BAGO BRIDGE (BO1827MN) ALONG RIZAL-DAKAK-DAPITAN COASTAL LOOP ROAD, ZN is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱3,563,759.00. Status: Reported complete (DPWH). Contractor on record: MONTPHIL CONST CORP. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Extension of Flood Control Structure (Revetment) along Dapitan River, Ilaya-Oyan Bridge including RROW section along Dipolog-Oroquieta Road, Dapitan City, Zamboanga del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-18-0014811

₱372,892.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱3,563,759.00

Progress

Reported complete (DPWH)

Start Date

March 23, 2018

Target End

May 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.