Buildings and Facilities18GH0024

CONSTRUCTION OF COVERED COURT (NORTHERN ILOILO POLYTECHNIC STATE COLLEGE AJUY CAMPUS), BRGY. POBLACION, AJUY, ILOILO

CONSTRUCTION OF COVERED COURT (NORTHERN ILOILO POLYTECHNIC STATE COLLEGE AJUY CAMPUS), BRGY. POBLACION, AJUY, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱1,959,424.59. Status: Reported complete (DPWH). Contractor on record: WOODLAND CONST. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,959,424.59

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

April 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.