Flood Control and Drainage19PA0026

CONSTRUCTION OF ISIT FLOOD CONTROL PROJECT DOLORES, ABRA STA. 0+000-STA. 1+580

CONSTRUCTION OF ISIT FLOOD CONTROL PROJECT DOLORES, ABRA STA. 0+000-STA. 1+580 is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱29,396,982.00. Status: Reported complete (DPWH). Contractor on record: A D MARRERO GEN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0014890

₱159,955.00 · FY2019

Released to Banquerohan National High School A an (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,396,982.00

Progress

Reported complete (DPWH)

Start Date

June 11, 2019

Target End

November 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.