Flood Control and Drainage23BH0262

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF BRGY. SINAOANGAN NORTE FLOOD CONTROL STRUCTURE, SECTION 3, SAN AGUSTIN, ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF BRGY. SINAOANGAN NORTE FLOOD CONTROL STRUCTURE, SECTION 3, SAN AGUSTIN, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱79,466,981.71. Status: Past target date (DPWH On-Going). Contractor on record: GACUTAN CONST INC FORMERLY: GACUTAN CONST 10789. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Villa Marzo Flood Control Structure, Section 1, Cordon, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 10789

52 projects · ₱2.6B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PALACIAN FLOOD CONTROL STRUCTURE, SECTION 1, SAN AGUS

Isabela 4th DEO, Region II

2025₱106.0M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CORDON BYPASS ROAD, ISABELA

Region II, Region II

2024₱98.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS ROAD AND DIVERSION ROADS - CORDON BYPASS ROAD, PACKAGE 1

Region II, Region II

2022₱97.9M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF VIRGONEZA FLOOD CONTROL STRUCTURE, SECTION 4, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF STA. ISABEL FLOOD CONTROL STRUCTURE, SECTION 2, JONES, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF MASAYA SUR FLOOD CONTROL STRUCTURE, SECTION 2, BRGY. MASAYA SUR, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
View all 52 projects →

4. Implementation

Contract Amount

₱79,466,981.71

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2024

Target End

January 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.