Roads19HG0163

LOCAL PROGRAM, LOCAL_ROADS_AND_BRIDGES, LOCAL ROADS, LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF ROAD, BRGY. TANGIL, DUMANJUG, CEBU

LOCAL PROGRAM, LOCAL_ROADS_AND_BRIDGES, LOCAL ROADS, LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF ROAD, BRGY. TANGIL, DUMANJUG, CEBU is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: QM BUILDERS. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-19-0006583

₱185,647.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

769 projects · ₱47.1B total · 123 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO -BRGY. MANLAPAY, DUMANJUG, CEBU

Region VII, Region VII

2025₱359.4M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), POBLACION, DUMANJUG, CEBU

Region VII, Region VII

2024₱313.6M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONST.OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE, AND LANDSLIDE, SECONDARY ROADS,CEBU TOLEDO WHARF ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING

Region VII, Region VII

2016₱295.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, ROAD CONCRETING OF SRP BACK ROAD (PHASE III)

Region VII, Region VII

2023₱289.4M
Past target date (DPWH On-Going)
No sat.

MF0-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES , SECONDARY ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING,) K0011+237-K0013+245, K0016+50

Region VII, Region VII

2017₱289.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF ROAD, BARANGAY LIBO-BARANGAY GUIBANGCO-AN, SIBONGA, CEBU PHASE 2

Region VII, Region VII

2025₱283.7M
Past target date (DPWH On-Going)
View all 769 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

November 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.