Buildings and Facilities24OG0117

IMPROVEMENT OF MULTI-PURPOSE MILITARY COMMUNITY CENTER (ENLISTED PERSONNEL), CAMP GENERAL EMILIO AGUINALDO, QUEZON CITY, PHASE III

IMPROVEMENT OF MULTI-PURPOSE MILITARY COMMUNITY CENTER (ENLISTED PERSONNEL), CAMP GENERAL EMILIO AGUINALDO, QUEZON CITY, PHASE III is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱9,796,946.88. Status: Reported complete (DPWH). Contractor on record: 4 DOUBLERS TRADING. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure along San Juan River ( Phase L ) , Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon City 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,796,946.88

Progress

Reported complete (DPWH)

Start Date

April 27, 2024

Target End

November 17, 2024

5. Audit