GAA 2025 SSP25AB0106

BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, MARIANO MARCOS STATE UNIVERSITY - BATAC CAMPUS, CITY OF BATAC, ILOCOS NORTE

BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, MARIANO MARCOS STATE UNIVERSITY - BATAC CAMPUS, CITY OF BATAC, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱48,024,900.00. Status: Past target date (DPWH On-Going). Contractor on record: MEGAPOLITAN BUILDERS AND CONST SUPPLY 38288. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱27,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation/Drainage Structure from Barangay San Francisco, Brgy. San Baltazar, Brgy. San Ildefonso, Brgy. San Bartolome, Brgy. San Silvestre and San Juan Bautista, San Nicolas, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 38288

320 projects · ₱5.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SRIP AND ITS APPURTENANT STRUCTURE, CABANGARAN SRIP, BARANGAY CABANGARAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱149.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 1, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 2, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, BARANGAY MABALENG, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱122.7M
Past target date (DPWH On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAOIT RIVER DIVERSION CANAL, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱115.8M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF SWIP, BARANGAY CAMANDINGAN, CITY OF BATAC, ILOCOS NORTE

Region I, Region I

2025₱112.3M
Past target date (DPWH On-Going)
View all 320 projects →

4. Implementation

Contract Amount

₱48,024,900.00

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

July 11, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.