Roads16HA0035

CONSTRUCTION OF DRAINAGE SYSTEM ALONG F. LIGASON STREET, BRGY. BOOL, TAGBILARAN CITY, BOHOL IST LD

CONSTRUCTION OF DRAINAGE SYSTEM ALONG F. LIGASON STREET, BRGY. BOOL, TAGBILARAN CITY, BOHOL IST LD is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱45,294,761.00. Status: Reported complete (DPWH). Contractor on record: SUPREME ABF CONST & CONST SUPPLY CO INC. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱11,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sagasa River Flood Control, Balilihan, Bohol, 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0027529

₱18,900,000.00 · FY2016

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱45,294,761.00

Progress

Reported complete (DPWH)

Start Date

October 28, 2016

Target End

April 30, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.