Roads19FO0060

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROAD, LIGAO-TABACO ROAD, K0507+323.20 - K0507+495.80

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROAD, LIGAO-TABACO ROAD, K0507+323.20 - K0507+495.80 is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱14,795,402.09. Status: Reported complete (DPWH). Contractor on record: ELKANKONSTRAK DEVELOPMENT CORP. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

57 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2024₱141.3M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - ALBAY WEST COAST ROAD (MARIGONDON SECTION), KO551 + 680.00 - KO552 + 1

Albay 3rd DEO, Region V

2024₱140.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-GUINOBATAN-JOVELLAR-DONSOL ROAD LEADING TO PILAR PORT, GUINOBATAN AND JOVELLAR, ALBAY, GU

Region V, Region V

2023₱102.4M
Past target date (DPWH On-Going)

Construction of Revetment along Downstream of Hamorawon Bridge, Pili, Camarines Sur

PILI (CAPITAL) (CAMARINES SUR), CAMARINES SUR, Region V

2023₱95.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱93.6M
Past target date (DPWH On-Going)
View all 57 projects →

4. Implementation

Contract Amount

₱14,795,402.09

Progress

Reported complete (DPWH)

Start Date

June 13, 2019

Target End

November 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.