GAA 2025 SSP25DM0042

CONSTRUCTION OF ROAD, SAN ISIDRO LEADING TO ELEMENTARY SCHOOL AND SITIO BAYEYE, MULANAY, QUEZON

CONSTRUCTION OF ROAD, SAN ISIDRO LEADING TO ELEMENTARY SCHOOL AND SITIO BAYEYE, MULANAY, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱14,400,376.62. Status: Reported complete (DPWH). Contractor on record: J. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation, Structure along Bingabing Creek, Brgy. Madulao, Catanauan, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,400,376.62

Progress

Reported complete (DPWH)

Start Date

April 4, 2025

Target End

August 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.