Flood Control and Drainage18A00107

REPAIR OF THE ZIGZAG SEAWALL AND ADJOINING ACCESS ROADS IN SITIO PUNTA, CABITTAOGAN, STA. CATALINA, ILOCOS SUR

REPAIR OF THE ZIGZAG SEAWALL AND ADJOINING ACCESS ROADS IN SITIO PUNTA, CABITTAOGAN, STA. CATALINA, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱36,293,458.04. Status: Reported complete (DPWH). Contractor on record: VIGAN FORTUNE CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱36,293,458.04

Progress

Reported complete (DPWH)

Start Date

June 1, 2018

Target End

October 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.