Roads22CJ0095

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) CONSTRUCTION OF MALUID - CRUZ DIVERSION ROAD, VICTORIA, TARLAC

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) CONSTRUCTION OF MALUID - CRUZ DIVERSION ROAD, VICTORIA, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱48,264,945.21. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Masalasa Creek, Tarlac City, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Tarlac DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,264,945.21

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

August 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.