Roads21IF0036

OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION - PALOMPON-ISABEL-MERIDA-ORMOC RD K1129+1012-K1130+888

OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION - PALOMPON-ISABEL-MERIDA-ORMOC RD K1129+1012-K1130+888 is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱9,309,671.23. Status: Reported complete (DPWH). Contractor on record: JSONS BUILDERS. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱9,625,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Dupong River, Brgy. Marvel, Isabel, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Leyte 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,309,671.23

Progress

Reported complete (DPWH)

Start Date

February 23, 2021

Target End

July 12, 2021

5. Audit