Flood Control and Drainage21CM0021

FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF PAMATAWAN RIVER (KANAYNAYAN SECTION), BRGY. SAN PABLO, CASTILLEJOS, ZAMBALES

FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF PAMATAWAN RIVER (KANAYNAYAN SECTION), BRGY. SAN PABLO, CASTILLEJOS, ZAMBALES is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱63,525,481.28. Status: Reported complete (DPWH). Contractor on record: R D SADSAD CONST. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Flood Control at Sto. Tomas River Downstream, North Approach, Sta. 0+308 - Sta. 1+008, San Felipe, Zambales
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zambales 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

48 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱63,525,481.28

Progress

Reported complete (DPWH)

Start Date

February 17, 2021

Target End

September 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.