Flood Control and Drainage20CJ0017

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SAN ISIDRO CREEK, TARLAC CITY, TARLAC

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SAN ISIDRO CREEK, TARLAC CITY, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱37,589,507.97. Status: Reported complete (DPWH). Contractor on record: CHIARA2300 INC. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along San Isidro Creek, Tarlac City, Tarlac
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Tarlac DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱37,589,507.97

Progress

Reported complete (DPWH)

Start Date

February 20, 2020

Target End

August 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.