Flood Control and Drainage20J00166

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL PROJECT AT DIPOLO RIVER - BRIDGE APPROACH, BRGY. UPPER TIMONAN, ZAMBOANGA DEL SUR

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL PROJECT AT DIPOLO RIVER - BRIDGE APPROACH, BRGY. UPPER TIMONAN, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱96,892,649.17. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,892,649.17

Progress

Reported complete (DPWH)

Start Date

November 23, 2020

Target End

November 11, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.