Water Provision and Storage23I00132

CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM FY 2023: 1. LGU GYMNASIUM, POBLACION DISTRICT 1, MCARTHUR LEYTE; 2. ABUYOG PUBLIC MARKET, ABUYOG, LEYTE; 3. BRGY. HALL, BRGY. BARAYONG, ABUYOG, LEYTE; 4. TOLOSA NATIONAL HIGH SCHOOL....., & OTHER 13 LOCATIONS

CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM FY 2023: 1. LGU GYMNASIUM, POBLACION DISTRICT 1, MCARTHUR LEYTE; 2. ABUYOG PUBLIC MARKET, ABUYOG, LEYTE; 3. BRGY. HALL, BRGY. BARAYONG, ABUYOG, LEYTE; 4. TOLOSA NATIONAL HIGH SCHOOL....., & OTHER 13 LOCATIONS is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱7,563,784.99. Status: Reported complete (DPWH). Contractor on record: ADB DYNAMIC BUILDERS. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

57 projects · ₱595.9M total · 0 flags

4. Implementation

Contract Amount

₱7,563,784.99

Progress

Reported complete (DPWH)

Start Date

November 15, 2023

Target End

May 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.