Construction of Flood Mitigation Structure24CE0193

Construction of Flood Control Structure along Labong River, Barangay San Juan, Licab, Nueva Ecija

Construction of Flood Control Structure along Labong River, Barangay San Juan, Licab, Nueva Ecija is a DPWH-tracked public work in LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱47,767,298.86. Status: Reported complete (DPWH). Contractor on record: M M SERRANO CONST CO. Figures trace to sumbong.

LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Labong River, Barangay San Cristobal, Licab, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0014806

₱50,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007110

₱2,098,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007111

₱193,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱47,767,298.86

Progress

Reported complete (DPWH)

Start Date

April 1, 2024

Target End

October 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.