Roads23CD0053

ORGANIZATIONAL OUTCOME 1 ASSET PRESERVATION PREVENTIVE MAINTENANCE TERTIARY ROADS - GEN. ALEJO SANTOS HIGHWAY K0065+354 K0065+570 ; K0066+703 K0067+000

ORGANIZATIONAL OUTCOME 1 ASSET PRESERVATION PREVENTIVE MAINTENANCE TERTIARY ROADS - GEN. ALEJO SANTOS HIGHWAY K0065+354 K0065+570 ; K0066+703 K0067+000 is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱13,860,086.83. Status: Reported complete (DPWH). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC 21923. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Maasim River along Maharlika Highway Phase 1, San Rafael Section (TP), Maasim, San Rafael, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 21923

207 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF REVETMENT AT MALANGAAN SECTION (SEGMENT A), DONA REMEDIOS TRINIDAD, BULACAN

Region III, Region III

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JOSE RIVER, STA. 08+320 STA. 08+620 (PARADA - SAN VICENTE SECTION), SANTA MARIA, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUYAN RIVER AND ITS TRIBUTIARIES, STA 04+000 STA 04+300 (LIPUTAN CONSTANTINO SECTION, RIGHT SIDE), MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2024₱96.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 3, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 4, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF REVETMENT AT MALANGAAN SECTION (SEGMENT B), DONA REMEDIOS TRINIDAD, BULACAN

Region III, Region III

2024₱95.1M
Past target date (DPWH On-Going)
View all 207 projects →

4. Implementation

Contract Amount

₱13,860,086.83

Progress

Reported complete (DPWH)

Start Date

May 22, 2023

Target End

August 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.