Flood Control and Drainage20DK0044

COMPLETION OF SPILLWAY @ IBABANG OWAIN, SAMPALOC, QUEZON

COMPLETION OF SPILLWAY @ IBABANG OWAIN, SAMPALOC, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱1,960,000.00. Status: Reported complete (DPWH). Contractor on record: V D DELIN CONST AND SUPPLIES. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱41,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Maapon River Flood Control, Sampaloc, Quezon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,960,000.00

Progress

Reported complete (DPWH)

Start Date

October 12, 2020

Target End

December 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.