Roads17J00129

ROAD WIDENING OF JOLO TAGLIBI TIPTIPON ROAD, SULU (1ST DEO), STA. 05+000.00 TO STA. 07+945.00, NET LENGTH: 5.89 LANE KM

ROAD WIDENING OF JOLO TAGLIBI TIPTIPON ROAD, SULU (1ST DEO), STA. 05+000.00 TO STA. 07+945.00, NET LENGTH: 5.89 LANE KM is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱83,670,378.85. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱83,670,378.85

Progress

Reported complete (DPWH)

Start Date

February 7, 2018

Target End

August 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.