Trust Funds 202424DB0157

CONCRETING OF BARANGAY LUMBANGAN FMR, BARANGAY LUMBANGAN, TUY, BATANGAS

CONCRETING OF BARANGAY LUMBANGAN FMR, BARANGAY LUMBANGAN, TUY, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱9,651,499.00. Status: Past target date (DPWH On-Going). Contractor on record: K M PALANCA CONST CORP. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Tubuan, Lemery, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Batangas 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

7 projects · ₱75.4M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONST OF MULTI-PURPOSE BUILDING AT CAMP RIEGO DE DIOS, TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2024₱14.7M
Past target date (DPWH On-Going)
No sat.

OPENING AND CONCRETING OF BRGY. POOK FMR, BRGY. POOK, BALAYAN, BATANGAS

Batangas 1st DEO, Region IV-A

2025₱14.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF BARANGAY REPARO FMR, BARANGAY REPARO, NASUGBU, BATANGAS

Batangas 1st DEO, Region IV-A

2024₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY AGUILA, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱12.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY TUGTUG, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱4.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SANTO CRISTO, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱4.8M
Reported complete (100% progress, DPWH status On-Going)
View all 7 projects →

4. Implementation

Contract Amount

₱9,651,499.00

Progress

Past target date (DPWH On-Going)

Start Date

June 5, 2025

Target End

October 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.