Bridges19E00041

RETROFITTING/STRENTHENING OF LUMINTAO BRIDGE ALONG MINDORO WEST COASTAL ROAD, MINDORO OCCIDENTAL

RETROFITTING/STRENTHENING OF LUMINTAO BRIDGE ALONG MINDORO WEST COASTAL ROAD, MINDORO OCCIDENTAL is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱134,995,460.12. Status: Reported complete (DPWH). Contractor on record: KEJAMARENIK CONST & CONST SUPPLIES 33742. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱134,995,460.12

Progress

Reported complete (DPWH)

Start Date

July 2, 2019

Target End

February 19, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.