Buildings and Facilities22BG0146

CONVERGENCE AND SPECIAL SUPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF BARANGAY HALL, BARANGAY ARA, BENITO SOLIVEN, ISABELA

CONVERGENCE AND SPECIAL SUPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF BARANGAY HALL, BARANGAY ARA, BENITO SOLIVEN, ISABELA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱2,856,663.40. Status: Reported complete (DPWH). Contractor on record: YZK BUILDERS. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pinacanauan River Flood Control Project, Brgy. Yeban-Sur-Maluno Norte, Benito Soliven, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Isabela 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,856,663.40

Progress

Reported complete (DPWH)

Start Date

July 11, 2022

Target End

November 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.