PROPOSED REHAB./IMPROVEMENT OF DRAINAGE SYSTEM ALONG CONCEPCION ST. FROM P. BURGOS ST. TO AYALA BLVD

PROPOSED REHAB./IMPROVEMENT OF DRAINAGE SYSTEM ALONG CONCEPCION ST. FROM P. BURGOS ST. TO AYALA BLVD is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱10,912,969.43. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱10,912,969.43

Progress

Reported complete (DPWH)

Start Date

February 19, 2016

Target End

May 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.