Buildings and Facilities19GL0109

CONSTRUCTION OF MULTI-PURPOSE BUILDING, ENCLARO, BINALBAGAN, NEGROS OCCIDENTAL BINALBAGAN, NEGROS OCCIDENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING, ENCLARO, BINALBAGAN, NEGROS OCCIDENTAL BINALBAGAN, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 2nd DEO, Negros Island Region. Reported contract value: ₱3,429,361.94. Status: Reported complete (DPWH). Contractor on record: BIG JOE'S ENT. Figures trace to dpwh.

Negros Occidental 2nd DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

29 projects · ₱311.0M total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROAD ALONG BACOLOD SOUTH ROAD, K0050+090- K0051+000, K0056+730- K0058+000, K0061+378- K0061+763, K0072+673- K0072+901.50, K0083+000- K0083+446,

Region VI, Region VI

2016₱48.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FARM TO MILL ROADS ATSITIONOLAN TO HILONGA, BRGY. MANSALANAO, LA CASTELLANA, NEGROS OCCIDENTAL

Negros Occidental 2nd DEO, Negros Island Region

2018₱31.1M
Reported complete (DPWH)
No sat.

ROAD WIDENING ALONG SECONDARY ROAD ON SPECIFIC LOCATION ALONG VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD (S00189NR) K0065+412.70-K0066+596.7, LA CASTELLANA, NEGROS OCCIDENTAL

Negros Occidental 2nd DEO, Negros Island Region

2020₱29.4M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE BASED ON PAVEMENTMANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) OF ISABELA-LIBAS-NEGROS OCCIDENTAL BDRY. ROAD, K0074+326-K0076+000, K0077+595-K0077+806, K0083+918-K0084+000, K0085+625-K0085+748, K0085+972-K0087+000

Negros Occidental 2nd DEO, Negros Island Region

2017₱24.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 1-UNIT 2-STOREY 10-CLASSROOM (9.5M X 55.00M) SCHOOL BUILDING AT HIMAMAYLAN NATIONAL HIGH SCHOOL

Negros Occidental 2nd DEO, Negros Island Region

2018₱24.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 1 UNIT THREE (3) STOREY REGULAR WORKSHOP BUILDING AT FLORENTINO GALANG, SR. NHS, KABANKALAN CITY, NEGROS OCCIDENTAL

Negros Occidental 3rd DEO, Negros Island Region

2018₱13.3M
Reported complete (DPWH)
View all 29 projects →

4. Implementation

Contract Amount

₱3,429,361.94

Progress

Reported complete (DPWH)

Start Date

September 5, 2019

Target End

November 23, 2019

5. Audit